Palmer Building Repurposing

Project Number
00-09609.00
Project Status
Complete - Architect/Engineer and Design/Build Selection
Complete - Construction Manager Selection and Other Services
Campus
University Park
Project Stage
RFP
Project Description

The existing art museum building is 51,013 GSF and is approximately 19,000 ASF of art galleries, art storage, art holding/prep/conservation, and the office/security/administrative functions of the museum. This project defines a complete change of space/use/function and full renovation/adaptive re-use/transformation of the facility, in addition to building system upgrades and building enclosure upgrades as required and defined herein. The Palmer Repurposing project has a total project cost of $40.4M, which includes a total construction cost of $30.4M.

Penn State Project Leader Name, Email
Architect/ Engineer and Design Build Selection