West Campus High-Pressure Steam Conversion Phase III

Project Number
00-08289.00
Project Status
Complete - Architect/Engineer and Design/Build Selection
Campus
University Park
Project Stage
Appointment Complete
Project Description

Modifications to steam utility system for conversion to high-pressure steam. Modifications within six existing steam manholes and installation of a new steam manhole south of Westgate Building. Pressure-reducing station modifications in Research Building West, Noll Lab, and Westgate. Temporary steam measures for the duration of the project.

Penn State Project Leader Name, Email
Architect/ Engineer and Design Build Selection
Capital Project (>$10M)
No
Attachments for Architect/Engineering and Design/Build Selection