Project Number
00-09218.00
Project Status
Trade/Bid Packages
Complete - Trade/Bid Packages
Campus
University Park
Project Stage
Out to Bid
Project Description

The primary scope of the Beaver Stadium renovation is on the stadium's West Side. This approach would replace the current West Side of the stadium and provide improved access for broadcasting, greatly improved circulation, new restrooms, upgraded concession offerings, and much-needed premium seating. Included with the West Side replacement are much-needed miscellaneous improvements of the North, East, and South, as listed below. These combined projects will greatly enhance the fan experience and safety and provide significant incremental revenue to fund these improvements.

Penn State Project Leader Name, Email
Architect/ Engineer and Design Build Selection
Capital Project (>$10M)
No
Professional Consultant
Company Name
Precis Engineering
Contact Name
John Volence
Email
jvolence@precisengineering.com
Construction Manager Selection and Other Services
CM Firm
Company Name
Barton Malow AECOM Hunt Alexander
Contact Name
Chris Stout
Phone
(814) 380-8003
Email
chris.stout@butz.com
Trade/Bid Package Information
Project Stage for Trade/Bid Package Information
Announcement
Prequalification

For their bid to be considered, bidders must be prequalified by Barton Malow. Prequalification information can be found within Building Connected/TradeTapp.

Additional Information

Bid through Building Connected. Prospective bidders should contact the CM team to discuss bid opportunities and receive access to the bid platform.

Bid Due Date and Time
Package Number Package Name Pre-Bid Date/Time Pre-Bid Meeting Bid Date/Time Awarded To Document
00-02 ECI - Structural Steel Sippel
00-03 ECI - Electrical Lighthouse
00-04 ECI - Low Voltage Lighthouse
00-06 ECI - Plumbing McClure
00-07 ECI - Mechanical McClure
00-08 Structural Precast ECI Not Awarded
00-09 Deep Foundations ECI Coastal Drilling East, LLC
00-10 Structural Precast ECI
01-03 2024 East Stadium Improvements - Deep Foundations Recommended but not Mandatory Coastal
01-04 2024 East Stadium Improvements - Site & Excavation Recommended but not Mandatory GOH
01-05 2024 East Stadium Improvements - Steel Recommended but not Mandatory Stewart Amos
01-06 2024 East Stadium Improvements - CIP Concrete Recommended but not Mandatory PJ Dick
01-07 2024 East Stadium Improvements - Plumbing Recommended but not Mandatory McClure
01-08 2024 East Stadium Improvements - Electrical Recommended but not Mandatory Hayden
01-09 2024 East Stadium Improvements - Metal Panels Recommended but not Mandatory Novinger's
01-10 2024 East Stadium Improvements - Masonry Recommended but not Mandatory Smith
01-11 2024 East Stadium Improvements - General Trades Recommended but not Mandatory Novinger's
01-12 2024 East Stadium Improvements - Roll-Up Gates Recommended but not Mandatory Novinger's
01-13 2024 East Stadium Improvements - Canopy Recommended but not Mandatory Novinger's
01-14 2024 East Stadium Improvements - Paint & Coatings Recommended but not Mandatory Saints
01-15 2024 East Stadium Improvements - Fire Protection Recommended but not Mandatory NOT AWARDED
00-01 Interior Demolition ISI Demolition
00-01 Early Contractor Involvement (ECI) Preconstruction - Selective Structural Demolition ISI Demolition
04-01 Interior Demolition Recommended but not Mandatory
04-02 General Trades Recommended but not Mandatory
04-03 Metal Studs, Drywall and Ceilings Recommended but not Mandatory
04-04 Flooring Recommended but not Mandatory
04-05 Paint Recommended but not Mandatory
04-06 Fire Protection Recommended but not Mandatory